Migration and operational readiness
Objective
The “tune it” phase is where the actual migration occurs, and the system is fine-tuned for optimal performance. This phase ensures all components are functioning correctly and the system is ready for live operation.
Tasks and Actions
1
Test Charger migration
Conduct migration tests on one charger per manufacturer to ensure data integrity and update the charger firmware according to the manufacturer's guidelines.
2
Test Site migration
Perform a full migration test of one site, containing only one charger manufacturer. If you are using several charger manufacturers, we recommend doing a Site migration per charger manufacturer in the beginning. If you have sites with a mix of manufacturers, we recommend doing them later when you have tested each manufacturer individually.
3
Execute Migration Plan
Follow the migration plan meticulously, ensuring all data is cleaned and structured correctly.
4
Migrate complete site data
Perform a full migration of site data, including chargers and users.
5
Troubleshooting and Update charger firmware
Update the charger firmware according to the manufacturer’s guidelines and troubleshoot any issues.
6
Start batch Migration
Now you can execute on the migration plan in full.